Cache Creek Culvert Replacement Update

Our team has completed the installation of the remaining bridge girders, marking a huge milestone in this Ministry of Transportation and Infrastructure project. This was an effort in collaboration with RKM Crane Services and other key partners including Yellowstone Traffic & Safety, who played a critical role in ensuring safe project execution and traffic management.

In addition to the girder placements, keyways have also been poured, with efforts now on laying the riprap and gravels beneath the bridge. Sidewalks are also to be poured on the east deck, with deck rebar installation also slated to begin soon.

Looking forward to providing further updates on this four-lane bridge project that is on pace for a fall completion.